Our biggest upgrade for this season was the new parking lot. A year ago I started the whole thing when I drained the pond.

After the pond was drained the initial grading was completed before last season. Then the wait was on for an erosion control permit.

About 8 months later we had a permit in hand and a new grading company taking on the job. After all the silt was removed the pipe was laid.
As more pipe was laid, more dirt was cut off the mountain to fill in the pond. The vertical cliff was removed and the dirt was put to good use.
After the dirt was in place and compacted, gravel made it feel complete.
The only thing left to do was hydro seed the upper bank.
And it was done, ready for some cars.
Two years ago when we took over this campground we had a vision of what we wanted it to be. We're one step closer.